Description
The Project involves the construction of a dual carriageway road bridge over the Swan River, between the alignment of the existing Fremantle Traffic Bridge and the existing Fremantle Rail Bridge.
The Project also includes the development, design and construction of an extension to the Fremantle Principal Shared Path (PSP) from the North Fremantle Station (north of the Swan River), over Tydeman Road and across the Swan River on the new road bridge.
A standalone rail bridge over the Swan River will also be constructed between the current alignments of the road and rail bridges, as well as modifications to the existing Fremantle Rail Bridge over the Swan River and rail bridges over Tydeman Road.
On completion, the Project will provide opportunities for improved river, road, pedestrian and cycling infrastructure to and from Fremantle. It will also facilitate improved freight and passenger rail access to Fremantle. This increased rail capacity will allow the shifting of container freight from road to rail, resulting in improved road network efficiency.
Rating Highlights
| Category | Credits | Achievements/Risks |
| General | V2.0 Planning | Swan River Crossings is the first ISC Planning Project to be verified on all targeted credits and levels – achieving 44.1 out of a targeted 44.1 points. |
| Heritage | Her-1 | Development of a Heritage Interpretation Strategy and Heritage Implementation Plan, balancing Aboriginal and historic heritage values through careful collaboration with Whadjuk Elders, heritage experts and the community via design forums. |
|
|
Sta-1, Sta-2 | Engaging with community and stakeholders on bridge alignment options and ensuring input in design development and urban outcomes. An example being consultation with regulators, State Design Review Panel and the Heritage Council to deliver an integrated design with sustainability at the core.
Early stakeholder engagement was responsible for a changed alignment of the Swan River Crossing bridge. Engagement consisted of a comprehensive three-week program of broad public consultation on the four proposed alignments:
The outcomes of the program have resulted in a clear preference for the proposed alignment of Option One. This option would place the two new bridges, road and rail, between the existing Fremantle Traffic Bridge and the existing rail bridge. The new rail bridge would have two tracks of rail. This option allows for the potential retention of a portion of the existing traffic bridge for heritage recognition purposes. A detailed analysis of qualitative feedback showed most people preferred Option One for the following reasons:
There was also a great outcome around Traditional Owner engagement, during the first Whadjuk Advisory Group Workshop (held 26 July 2021) the elders introduced the project team to the notion of totems flowing through the river and the need to remove / minimise piers in the river. At the second Whadjuk Advisory Group Workshop (30 August 2021) Anthony Deurloo, Project Alliance Director, confirmed to the group that the project has further reduced five piers down to three. Further reducing the number of piers from the original bridge ~200 to 36 on the new bridge. |
| Environmental Impacts |
|
Undertaking of baseline studies for all environmental aspects that informed SMART goals for the construction and operation of the assets.
Identifying opportunities to reduce GHG and noise emissions through use of renewables and green power, as well as sourcing hybrid and electric plant. |
| Context | Con-2 | Urban and Landscape Design Framework and Strategy informing design for green infrastructure and WSUD to promote ecological diversity and provide riverine enhancement. |
Verified Innovations
| Name | Verification Date | Description |
| Road and Rail Bridge – Long Launch Bridge Span Length and Construction Type | 28/06/2022 | The structural form of the bridges is highly innovative and makes the most of advancements in high strength concrete technology. The design of the bridge includes straight vertical webs over the bearings to push the span arrangements to the limit of what has previously been launched in Australia, with spans of over 71m without the need for intermediate piers.
|