Raising London Circuit

Project Details

  • Rating Type: As Built
  • Location: ACT
  • Rating Level: Excellent
  • Rating Score: 68.83
  • Assessor Name: Holly Hofland, Kazumi Yamada
  • IS Project manager: Luke Sammut
  • Stakeholders: Infrastructure Canberra, Abergeldie Complex Infrastructure, AECOM, Roads ACT + Community and Environment Directorate + National Capital Authority

Description

The Project involved raising London Circuit between Edinburgh Avenue and Constitution Avenue on a gradual filled embankment to meet the current height of Commonwealth Avenue, and provision of a new signalised intersection between London Circuit and Commonwealth Avenue.

Key features of The Project involve:

  • Temporary closure of London Circuit between Edinburgh Avenue and Constitution Avenue
  • Infilling the London Circuit Road reserve between Edinburgh Avenue and Constitution Avenue, to form embankments from the intersections with those roads to around the existing height of Commonwealth Avenue
  • Removal of the existing ramps (cloverleaves) to the north west and southwest of the London Circuit-Commonwealth Avenue interchange and modification of the existing ramp to the south east to remove connection with London Circuit and retain connection between Parkes Way and Commonwealth Avenue
  • Staged closure and demolition of the northbound and southbound Commonwealth Avenue bridges over London Circuit, including infilling the London Circuit road reserve below
  • Rebuilding London Circuit between Edinburgh Avenue and Commonwealth Avenue
  • Rebuilding London Circuit between Commonwealth Avenue and Constitution Avenue
  • Building a new signalised London Circuit-Commonwealth Avenue intersection, including capacity to accommodate proposed and potential future light rail infrastructure
  • Provision of active transport infrastructure, utility connections, lighting, street furniture, landscaping and drainage
  • Ancillary activities include construction compound sites, traffic diversions and traffic management measures.

Rating Highlights

Category Credits Achievements
Stakeholder Participation Sta-2 The project actively engaged stakeholders throughout planning and delivery to ensure community needs, expectations, and project outcomes were effectively addressed.
Heritage Her-1 The project identified, protected, and appropriately managed heritage values to preserve cultural and historical significance that is specific to the ACT.
Climate Change Adaptation Cli-1 The project consistently considered climate-related risks and opportunities within decision-making processes to support long-term resilience and sustainability.
Management Systems Man-6 The project consistently demonstrated effective management systems, governance practices, and continuous improvement throughout all phases of delivery.

Verified Innovations 

Name  Innovation Type Description
Passive Street tree Irrigation First innovative technology or process – State First Increasing stormwater capacity and storage while supporting passive tree irrigation demonstrates a truly sustainable design. The passive irrigation design addresses issues of irrigation water use and wastage, the diversion of run off of potential contaminant loads into nearby water bodies (Lake Burley Griffin) and the need to be resilient against high flood load
Revizto Digital Engineering First innovative technology or process – State First Use of a 3D planning tool and model to undertake options analysis and demonstrate designs to stakeholders. This resulted in a 3D real-time model linked to digital 3D design model that can be accessed on site
OPC reduction Market transformation Inclusion of project specific specification that sets OPC reduction target of 40% across all concrete used on RLC
Peri-Duo reusable formwork First innovative technology or process – State First DUO uses advanced technopolymer material which offers lightweight durability, versatility, and sustainability through reuse. The innovative composite formwork provides the strength of traditional materials while being significantly lighter, and can be reused ongoing without compromising the integrity of the structures.

 