Project Details

  • Rating Type: Design
  • Location: NSW
  • Rating Level: Excellent
  • Rating Score: 57.2
  • IS Project manager: Haslin Constructions
  • Stakeholders: Haslin Constructions,Arcadis,Sydney Trains ,Transport for NSW (TfNSW)

Description:

The Transport Access Program (TAP) is an initiative by the NSW Government, dedicated to enhancing the accessibility and convenience of public transport infrastructure across the state. For this project the Denistone and Stanmore railway station scopes are centred around improving public transport access for individuals with disabilities, limited mobility, and parents or carers with prams. 

Rating Highlights 

Category  Credits  Achievements/Risks 
Climate Change Adaptation  Cli-2  The Project achieved a verified level of 3 with a score of 2.89.  

The Project identified one high priority risk related to extreme rainfall causing flooding and blockages to drainage systems and culverts. Subsequently, a proposed drainage system design was implemented resulting in a medium residual risk rating. Other mitigation measures implemented to reduce extreme heat related risks include:  

  • Installing a fan to be activated when the lift shaft internal temperature reaches 32°C. 
  • Including additional redundancy in intelligent transport system infrastructure and smart motorways in design. 
Community Health, Well-being and Safety   Hea-1  The Project achieved a verified level of 3 with a score of 2.89.  

The Project identified three community priority issues to positively contribute to: 

Priority Issue  Initiative  
Increasing education opportunities  Promoting social procurement and workforce development through project targets  
Improving representation of cultural diversity   Incorporating Indigenous artwork in the lift foyer at Stanmore station   
Promoting active transport   Upgrading bike hoops at Stanmore station and existing cycleways  

 

Verified Innovations 

Name   Verification Date  Innovation Type   Description & Sustainability Benefits 
ISupply  6/10/23    Innovation Challenge (IC-8)  The Project received 0.75 points for using the following services/products from the ISupply Directory:  

  • Bingo Industries (waste disposal) 
  • Boral (concrete) 
  • Infrabuild (reinforcement steel) 
  • Xypex Admix C (additive in Boral concrete mix) 

 

Certification Date:   

8-May-24